Downtown Crossing Look Ahead: Weeks of Nov. 18 & Nov. 25

Downtown Crossing Look Ahead: Weeks of Nov. 18 & Nov. 25

Downtown Crossing Look Ahead: Weeks of Nov. 18 & Nov. 25

Print
Email
|

News Release

Posted on November 22, 2013 at 5:15 PM

The following closures and lane restrictions are expected this week and next week in connection with construction on the Downtown Crossing:

Work Currently Underway:

Louisville Streets:

•    Lane restrictions are expected on Witherspoon Street from Preston Street to Adams Street through Saturday, November 23 for utility work and pile driving.  One lane of traffic will be open in each direction.
•    The right lane of westbound Witherspoon Street from River Road to Adams Street is scheduled to be closed through Tuesday, December 10 for work on a retaining wall.
•    The left lane of Main Street from Hancock Street to Jackson Street is scheduled to be closed through Wednesday, November 27 for work on retaining walls.
•    The right lane and right parking lane on eastbound Market Street from Jackson Street to Hancock Street are scheduled to be closed through Wednesday, November 27 for abutment work.
•    The right lane and right parking lane on Preston Street from Market Street to Liberty Street are scheduled to be closed through Friday, December 20 for pile driving.
•    The left lane and both parking lanes on Jefferson Street from Jackson Street to Preston Street are scheduled to be closed through Friday, December 20 for pile driving and excavation work.
•    The left lane of Jackson Street from Jefferson Street to Market Street is scheduled to be closed through Monday, November 25 for abutment work.
•    The right lane and left lane of Liberty Street from Floyd Street to Preston Street are scheduled to be closed through Saturday, December 7 for excavation and demolition work.

Work Scheduled for This Week:

Kentucky Side:

Work scheduled for Friday, November 22:

•    The right lane of I-71 South from Frankfort Avenue to the merge with I-64 West is scheduled to be closed overnight Friday, November 22 for work on a temporary wall.  It’s expected to close around 9 p.m. and reopen by 5 a.m.
•    The ramp from I-71 South to I-64 West is scheduled to close overnight Friday, November 22 for work on a temporary wall.  It’s expected to close around 9 p.m. and reopen by 5 a.m.
•    The ramp from I-64 East to I-65 North is scheduled to close overnight Friday, November 22 for work on a temporary wall.  It’s expected to close around 9 p.m. and reopen by 5 a.m.

Louisville Streets:

Work scheduled to begin Saturday, November 23:

•     Lane restrictions are expected on Witherspoon Street from Preston Street to Clay Street Saturday, November 23 through Friday, December 20 for utility work and pile driving.  One lane of traffic will be open in each direction.

Work Scheduled for Next Week:

Kentucky Side:

Work scheduled for Monday, November 25:

•    The right lane of I-64 East from the I-71 North exit ramp to 1000 feet east of the ramp is scheduled to close overnight Monday, November 25 for temporary paving.  It’s expected to close around 9 p.m. and reopen by 5 a.m.

Louisville Streets:

Work scheduled to begin Monday, November 25:

•    Jackson Street from Jefferson Street to Market Street is scheduled to be closed Monday, November 25-Wednesday, December 4 for work on a storm sewer.

Continuing Closures and Restrictions:

Kentucky Side:

•    The ramp from I-64 East to I-65 South closed July 15 and is scheduled to be closed through the spring of 2016.
•    The right lane of I-65 South from the Jefferson Street ramp to Muhammad Ali Boulevard closed July 15 and is scheduled to be closed through 2016.
Indiana Side:
•    Broadway Street has closed from Court Avenue to 6th Street.  This includes the closure of the 6th Street ramp to I-65 North.  These are permanent closures.
•    7th Street has closed from Missouri Avenue to Broadway Street.  This is a permanent closure.
•    VFW Boulevard has closed from 7th Street to 9th Street.   This is a permanent closure.
•    US 31-South (Exit Ramp 1) from Brown Station Way to Stansifer Avenue has been reduced to two lanes.
•    US 31-South, in the area just south of Stansifer Avenue, has been reduced to one lane.  Vehicles are still able to exit onto 10th Street.
 

Print
Email
|