Bridges Project: Work, closures scheduled for Sept. 6 - 10

Bridges Project: Work, closures scheduled for Sept. 6 - 10

Bridges Project: Work, closures scheduled for Sept. 6 - 10

Print
Email
|

by News release

WHAS11.com

Posted on September 6, 2013 at 1:21 PM

Updated Sunday, Sep 8 at 3:57 PM

LOUISVILLE, Ky. (September 6, 2013) – The following closures and lane restrictions are expected today and next week in connection with construction on the Downtown Crossing:

Work scheduled for Friday, September 6

Kentucky Side:

  • The ramp from I-71 South to I-64 West is scheduled to close overnight Friday, September 6 for the placement of temporary barrier wall.  It’s scheduled to close around 9 p.m. and reopen by 5 a.m.

Louisville Streets:

 

  • The right lane of Jackson Street from Market Street to Main Street is scheduled to be closed Friday, September 6 for utility work.
  • Lane restrictions are scheduled at Jefferson Street and Preston Street on Friday, September 6 for work in the area.


Work scheduled for Monday, September 9

Kentucky Side:

  • The ramp from I-71 South to I-64 West is scheduled to close overnight Monday, September 9 for the placement of temporary barrier wall.  It’s scheduled to close around 9 p.m. and reopen by 5 a.m.

Louisville Streets:

  • Lane restrictions are scheduled at Jefferson Street and Preston Street Monday-Friday (September 9-13) for work in the area.
  • The right lane of Jackson Street from Market Street to Main Street is scheduled to be closed Monday-Friday (September 9-13) for utility work.
  • The right lane of Hancock Street from Market Street to Main Street is scheduled to be closed Monday-Friday (September 9-13) for utility work.


Indiana Side:

  • 7th Street will be closing from Missouri Avenue to Broadway Street.  The closure is expected Monday morning.  This is a permanent closure.
  • Vfw Boulevard will be closing from 7th Street to 9th Street.   The closure is expected Monday morning. This is a permanent closure.


Work scheduled to begin Tuesday, September 10


Kentucky Side:

  • The ramp from I-64 East to I-71 North is scheduled to close overnight Tuesday-Thursday (September 10-12) for work on temporary lighting.  It’s scheduled to close around 9 p.m. and reopen by 5 a.m. each day.

Louisville Streets:

  • The right lane of Main Street from Hancock Street to Jackson Street is scheduled to be closed Tuesday-Friday (September 10-13) for work in the area.
  • Overnight lane restrictions are expected on Main Street from Hancock Street to Jackson Street Tuesday and Wednesday (September 10-11) for storm sewer work.  One lane will be open in each direction.  The lanes are scheduled to close around 7 p.m. and reopen by 5 a.m.

Continuing Work

Kentucky Side:

  • The ramp from I-64 East to I-65 South closed July 15 and is scheduled to be closed through the spring of 2016.
  • The right lane of I-65 South from the Jefferson Street ramp to Muhammad Ali Boulevard closed July 15 and is scheduled to be closed through 2016.

Indiana Side:

  • US 31-South (Exit Ramp 1) from Brown Station Way to Stansifer Avenue will be reduced to two lanes for the next several months.
  • US 31-South, in the area just south of Stansifer Avenue, will be reduced to one lane for the next several months.  Vehicles are still able to exit onto 10th Street.

Print
Email
|